Generali Stadium: Latest on AC Milan and Inter’s new San Siro home

Generali Stadium: Latest on AC Milan and Inter’s new San Siro home
Concept image of the Generali Stadium - Photo via AC Milan

Generali Stadium is the 71,500-seat new home that AC Milan and Inter plan to open next to San Siro in time for the 2031/32 season.

Designed by Foster + Partners and MANICA, it was unveiled on October 29 2026, and would end almost a century of football at the Giuseppe Meazza, which opened in 1926.

Planning approval is now the hurdle, after Milan City Council voted on November 9 to ask for a health impact assessment that could slow the process.

FootballGroundGuide tracks the project below, from the land deal to the approvals still needed before construction begins.

Generali Stadium – project timeline

Last update: 20 November 2026
71,500Capacity
c. €1.2bnStadium cost (reported)
c. €2.3bnWhole project (reported)
2028Construction start (target)
2031/32First match (target)
  • Land purchase
  • Design
  • Planning & approvals
  • Construction
  • Opening
  • San Siro partial demolition
  1. AC Milan and Inter unveil shortlisted designs – Populous and MANICA concepts for a new stadium in the San Siro area are put to fans and the City of Milan.
  2. Populous's ‘The Cathedral’ selected – the clubs pick a design that never reaches construction.
  3. UEFA rules San Siro out of Euro 2032 – the Giuseppe Meazza does not meet the tournament's venue requirements, putting the focus on a new stadium.
  4. Milan City Council approves the sale – San Siro and the surrounding land go to AC Milan and Inter for €197m after a 24–20 vote.
  5. Sale completed – the deed is signed on November 5, days before a heritage protection order on the second tier would have taken effect.
  6. Environmental assessment launched – the City of Milan opens the strategic environmental assessment (VAS) of the San Siro implementation plan.
  7. First preparatory works – the Biglietteria Sud ticket office is demolished and some turnstiles are moved back.
  8. Milan included in Euro 2032 bid – the Italian Football Federation sends UEFA dossiers for 14 stadiums, with Milan's entry based on the new stadium.
  9. Court clears the sale – the regional administrative court for Lombardy rejects or rules inadmissible all five appeals.
  10. Generali Stadium unveiled – the Foster + Partners and MANICA design is revealed at the Castello Sforzesco on October 29.
  11. Council asks for health impact assessment – a 22–6 vote calls for the VAS to be suspended; mayor Beppe Sala says he will not rethink the process.
DoneCurrent stageExpected

Generali Stadium latest news

November 2026 update: Council vote asks for health checks before approval

Milan City Council approved a motion by 22 votes to six on November 9 calling for the strategic environmental assessment (VAS) of the San Siro plan to be suspended and restarted alongside a health impact assessment.

Councillors want the study to cover the effects of partly demolishing the Meazza, removing waste and cleaning up the site, with specific attention to schools, children and elderly residents nearby.

The motion is not binding on the city's executive, and Beppe Sala responded that he respects the council's view but has no intention of rethinking the process.

Support for the motion came from the centre-right opposition and part of Sala's own centre-left majority, and this is the first time the council has pushed back on the new stadium.

October 2026 update: Generali Stadium name and design revealed

The clubs presented the name and design on October 29 at the Castello Sforzesco, where a scale model went on free public display until November 1.

Generali, Italy's largest insurer, will be the naming partner from opening day and is now also the official insurance partner of both clubs.

The joint statement from AC Milan and Inter did not disclose the value of the naming deal, although reports in Italy put it at €650m (around £543m) over 20 years.

The same statement targets the start of construction in 2028 and a first match in the 2031/32 season, with both dates subject to approvals.

October 2026 update: Court clears the San Siro sale

On October 6, the regional administrative court for Lombardy (TAR) rejected or declared inadmissible all five appeals against the sale of San Siro to the clubs, the oldest of which was lodged in 2022.

A criminal investigation by Milan prosecutors into the sale, on suspicion of bid-rigging and disclosure of official secrets, remains open.

October 2026 update: Milan included in Italy's Euro 2032 bid

The Italian Football Federation (FIGC) sent UEFA its dossiers for 14 stadiums in 13 cities by the October 1 deadline, with Milan's entry built around the new stadium project.

UEFA has said that work on new or rebuilt venues must begin by March 2027 for them to be considered for Euro 2032, which is earlier than the 2028 start in the clubs' own timetable.

June 2026 update: First preparatory works at San Siro

Demolition of the Biglietteria Sud, the stadium's south ticket office, began on June 23 to clear space for future works.

Turnstiles at several entrances behind the main stand were moved back as part of the same preparatory works ahead of the 2026/27 season.

March 2026 update: Environmental assessment begins

The City of Milan launched the VAS of the implementation plan for the San Siro area on March 23, 2026, after a proposal from the clubs' joint company, Stadio San Siro S.p.A.

For the land sale, the Winter Olympics opening ceremony and earlier plans for the site, read our full San Siro demolition updates.

Generali Stadium features: What will the new San Siro look like?

Generali Stadium will have two seating tiers forming a continuous 360-degree bowl, with two steep single-tier Curvas behind the goals raked at up to 37 degrees.

An exposed concrete X-frame runs from the colonnades at ground level through the facade and supports a double-curved roof designed to trap crowd noise.

Diamond-shaped entrances lead up to panoramic concourses, and the clubs promise seating ranging from popular areas to premium hospitality.

Solar panels on the roof and natural ventilation are the main sustainability measures in the published plans.

The stadium sits inside a 281,000 square-metre regeneration of the district, with public spaces, green areas, shops and leisure venues designed to be used year-round.

FootballGroundGuide has looked at five of the standout design details of Generali Stadium in more depth.

Generali Stadium vs San Siro
Generali Stadium
Planned, next to the current ground
Capacity71,500
First match2031/32 (target)
Seating tiersTwo
EndsSingle-tier Curvas, up to 37°
ArchitectsFoster + Partners and MANICA
OwnersAC Milan and Inter
San Siro (Stadio Giuseppe Meazza)
Current home of both clubs
Capacity75,817
Opened1926
Seating tiersThree (third added for 1990)
EndsCurva Nord and Curva Sud
Named afterGiuseppe Meazza (since 1980)
OwnersAC Milan and Inter (since 2025)
Generali Stadium figures are the clubs’ published plans and remain subject to planning approval.

When will Generali Stadium open?

AC Milan and Inter are targeting the 2031/32 season for the first match at Generali Stadium, with construction due to start in 2028.

Both dates are conditional on approvals, and the 2028 start is later than the second half of 2027 that the City of Milan was aiming for in March 2026.

According to reports in Italy, the next steps are the close of the VAS, a preliminary feasibility project and sign-off on the final design by the city, the Lombardy Region, the metropolitan city, the fire service and the local health authority.

A 2028 start would fall after UEFA's March 2027 deadline for work on Euro 2032 venues to begin, so the date construction starts will decide whether Milan stages matches at the tournament in June and July 2032.

Generali Stadium approvals tracker
What still has to happen before work starts · Last update: 20 November 2026
Done
San Siro and surrounding land bought€197m deed signed on November 5, 2025.
Done
Legal challenges to the saleAll five appeals rejected or ruled inadmissible by the Lombardy administrative court on October 6, 2026.
Done
Design and name revealedFoster + Partners and MANICA plans presented on October 29, 2026.
At risk
Strategic environmental assessment (VAS)Under way since March 23, 2026. The council voted 22–6 on November 9 to ask for it to be suspended and paired with a health impact assessment.
Pending
Final project approvalSign-off needed from the City of Milan, the Lombardy Region, the metropolitan city, the fire service and the local health authority.
Pending
Start of constructionClubs target 2028. UEFA wants work on Euro 2032 venues under way by March 2027.
Open
Prosecutors’ investigationMilan prosecutors are investigating the sale on suspicion of bid-rigging and disclosure of official secrets.

How much will Generali Stadium cost?

The clubs have not published a cost, but the stadium itself is reported at around €1.2bn (about £1bn).

Project documents reported in Italy put the total investment at €2.3bn (about £1.9bn), covering the land purchase, the new stadium, the partial demolition of the Meazza, commercial space and infrastructure.

That total includes the €197m that AC Milan and Inter paid the City of Milan for San Siro and the surrounding land in November 2025.

The clubs' owners, RedBird Capital Partners at AC Milan and Oaktree at Inter, are leading the investment, and the reported Generali naming deal offsets part of the bill.

Where will AC Milan and Inter play while Generali Stadium is built?

Both clubs will stay at San Siro throughout construction, because Generali Stadium is being built on land next to the current ground rather than on its footprint.

Once the new stadium is in use, the Meazza is due to be partly demolished, with the rest of the site turned over to the new district.

For tickets, transport and matchday advice at the current ground, see our AC Milan and Inter Milan stadium guide.

FGG says: Generali Stadium's real deadline is March 2027, not 2031

Milan has been here before, with shortlisted designs in 2019 and Populous's 'Cathedral' in 2021 both failing to reach construction.

This time the clubs own the land, the court challenges to the sale have failed, and a named partner is paying for the right to brand the stadium.

The council's 22-6 vote shows the political risk has not gone away, and every month added to the VAS pushes the first spade further from UEFA's March 2027 cut-off.

Missing that date would not stop Generali Stadium being built, but it would leave Milan without a Euro 2032 venue.

Generali Stadium FAQs

What is the capacity of Generali Stadium?

Generali Stadium will hold around 71,500 spectators, slightly fewer than the 75,817 capacity of the current San Siro.

When will Generali Stadium open?

AC Milan and Inter are targeting the 2031/32 season for the first match, subject to approvals.

Where is Generali Stadium being built?

It is being built in the San Siro district of Milan, on land next to the existing Stadio Giuseppe Meazza.

Who designed Generali Stadium?

The design is by Foster + Partners and MANICA.

Will San Siro be demolished?

The Meazza is due to be partly demolished once Generali Stadium is in use, with both clubs playing at San Siro until then.

Is Generali Stadium the same as the Generali Arena?

No, the Generali Arena is the home of Austria Vienna, while Generali Stadium is the new Milan ground shared by AC Milan and Inter.

Articles: 3